Allocation accuracy by organization nodes / by person / by projects
This report gives you a color-coded look on allocations based on your preferred choice (organization node, person, projects).
The chosen view mode and allocation units (top-right corner) are taken into account
When using the "Days" option under 'Allocation units' the calculations are always based on the system default workday length (usually 7,5 or 8,0 hours)
The color-coding in the report is based on values in any particular slot:
- Actual hours
- Allocated hours
- Maximum hours of the corresponding slot
for these values:
(Allocations - Actuals) / Maximum hours of corresponding slot * 100%
(negative values are handled as positive values)
Corresponding color for the value from the equation:
When viewing the report by Projects the project's unassigned roles are also reported and exported.