The graph has both HOURS and CURRENCY ("EUR") mode. In both views you can dictate what data is shown by using the sliders in the legend located top-right of the graph.
- The data is always shown in monthly mode.
- The data can be viewed in all four of Silverbucket's resourcing modes.
- Confirmed, confirmed & tentative, tentative & confirmed, tentative
- By hovering over the data, you can see more precise values.
Show Raw Data shows the project in numbers. It shows the core data related to resourcing, allocations and everything related to the project. It is shown when you click the SHOW RAW DATA button.
Estimated income budget for the project. Edited by clicking.
Budgeted hours for the project. Edited by clicking.
Estimated expense budget for the project. Edited by clicking.
Cumulative sum of all the allocations for the project.
Cumulative sum of all the allocations * forecast price from task / role.
Cumulative sum of all the allocations * cost price from role.
Allocations (EUR) - Allocations, cost price (EUR).
Cumulative sum of all the actual hours registered for the project.
Cumulative sum of all the actual hours registered for the project * price from task / role.
A simple view to check your project's progress:
- Left pie shows the manual readiness of the project. Manual readiness is adjusted under BASIC tab
- Right pie is calculated by Time Budget - Realization Hours. Time Budget is adjusted in PLANNING view and Realization hours is calculated automatically by hours registered for the project.
A simple risk management tool where you evaluate four different risk scenarios: schedule, budget, scope & resourcing. You can evaluate a PROBABILITY value and IMPACT value for each risk. These are then multiplied together to calculate the RISK RATING.
Editing the PROBABILITY and IMPACT values is done by clicking on a value. In the opening view you can also add notes regarding the risks for the project if you wish.
"Realized" slider dictates whether or not the risk has happened or not