Projects Planning view is your go-to place when viewing multiple projects at once. You can user the filtering to only show projects relevant to you.
Add a caption...
All the filtered projects are listed on the left side of the screen. By default, individual project's resourcing plan is collapsed but it can be expanded by clicking the chevron icon just right of the name.
Pies
Add a caption...
TARGET
Project's OWN INCOME, EXTERNAL INCOME & OTHER INCOME (edited by clicking the pen icon)
TIME-BASED
Project's monthly hours based budget / Project's time budget (own + external)
TASK-BASED
Project's tasks' budget / Project's time budget
RESOURCE-BASED
Project's projectroles' budget / Project's time budget
Buttons, modes and icons
Add a caption...
Left arrow moves you back in time in the resourcing section
Home icon brings you to current date
Calendar icon allows you to select a specific date
Right arrow moves you forward in time
Add a caption...
NO GROUPING / USER / ROLE / TASK dictates how the data is grouped in the view
With TASK selection a pie icon is visualised next to the rows
Calculation: actual hours registered for the task / Task's budget
CONFIRMED / TENTATIVE dictates which resourcing universe is shown
Time modes: DAY / WEEK / MONTH / QUARTER
View modes: HOURS / RELATIVE
Add a caption...
Solid slot = Viewing confirmed resourcing
Slot symbolized with an "envelope" = Viewing confirmed resourcing but the slot also has tentative resourcing
Add a caption...
Slot symbolized with a "diameter" = Viewing tentative resourcing but the slot also has confirmed resourcing
Collapsed resourcing view
Add a caption...
In the collapsed view, singular projects' resourcing slots are colored with shades of white and green. In this view, Silverbucket checks for the highest valued slot and opaques the rest of the slots in correlation to the highest resourced slot:
A dark green slot is the most resourced slot
A fully white slot is the least resourced slot
Grey slots are slots with no resourcing
Similarly, the total row in the top shows values in shades of white and blue
Dark blue is the most resourced total slot
A fully white slot is the least resourced total slot
Grey slots are slots with no resourcing
This coloring gives you a quick glance on the approximate resourcing situations for projects, sort of like a heatmap.
Detailed resourcing view
You can view projects in a more detailed manner by clicking the chevron icon next to it. Once clicked, you are shown more detailed resourcing values - based on the selected view mode.
Add a caption...
The coloring is based on the slot's resourcing value. The coloring is the same as in the previous version of Silverbucket: from light yellow to dark red with green color as the sweet 100% spot. Grey color means that there is no resourcing at all in that slot.
The resourcing slots also include a small line in the bottom of the slot if the person is resourced for any other project for the same time slot: shades of green mean that the person is not over-resourced and all is good, while red color means that the person's capacity is exceeded and you should re-consider the resourcing plans for that person.
Detailed information numbers
Click the calculator icon to see more information regarding the project roles:
This sketch cannot currently be displayed in exports
Note: calculations might show N/A if that value can't explicitly be shown for that row; try out the different grouping options above ("Group by: *") if you are seeing N/A values.
EUR / HOUR = Hourly rate; can be adjusted in the Edit Project Role modal
ACTUALS HOUR = Past actual hours registered
PLANNED HOUR = Resourced hours in the future
ACTUALS + PLANNED = Actual hours from the past + resourced hours from the future
BUDGET HOUR = Budget hour for the project role; can be adjusted in the Edit Project Role modal
BUDGET (-ACTUALS-PLANNED) = Hour budget - actual hours from the past - resourced hours from the future